What Is a CCC? Building Approvals Explained
Pasukan RumahHQ · Published 24 September 2026 · Updated 24 September 2026 · 14 min read
In brief
- Without a CCC, the developer cannot deliver vacant possession under the statutory SPA, and occupying the home is itself an offence.
- Since 2007 the PSP, not the local authority, issues the CCC in Form F. A partial CCC (Form F1) is not enough for VP under a Schedule G SPA.
- Ask for Form F before collecting the keys, check the lot, plan reference and PSP, and note the CCC date: the 12-month LAD claim period runs from it.
Before you receive the keys to a new home, one document must exist: the Certificate of Completion and Compliance, or CCC. Without it, the developer cannot deliver vacant possession under the statutory SPA, and occupying the home is itself an offence. Yet many buyers have never seen their home’s CCC, and do not know what to check.
This guide explains the whole approval journey of a housing project: planning permission, building plan approval, construction with the stage certification Forms G1 to G21, the issue of the CCC by the Principal Submitting Person (PSP), and finally the delivery of vacant possession. You will also learn why the CCC matters to you and how to check it. General information only, not legal/financial/tax advice.
Key terms
- Act 133: the Street, Drainage and Building Act 1974, the law under which local authorities control the construction of buildings.
- UBBL: the Uniform Building By-Laws 1984, made under Act 133. Amendment K.P.U. 6/2007 introduced the CCC system.
- Act 172: the Town and Country Planning Act 1976, which governs planning permission.
- Local authority: for example a municipal or city council.
- Planning permission (kebenaran merancang, KM): approval of the land use and layout of a development.
- Qualified person: a professional architect, professional engineer or building draughtsman registered under the relevant law.
- PSP (Principal Submitting Person): the qualified person who submits the building plans to the local authority for approval.
- SP (Submitting Person): a qualified person who submits plans other than building plans, for example earthwork or structural plans, to the local authority or the relevant statutory authority.
- CCC: the Certificate of Completion and Compliance, issued in Form F. A partial CCC is issued in Form F1.
- VP: vacant possession, the handover of the home and keys to the buyer.
The approval flow: from empty land to keys
- Planning permissionThe local planning authority approves the land use and layout under Act 172
- Building plan approvalThe PSP submits the building plans to the local authority
- Construction: Forms G1 to G21Each building component is certified one by one
- CCC by the PSPForm F is issued once every condition in by-law 25 is met
- Vacant possession (VP)The home and keys are handed over; water and electricity ready for connection
- Planning permission The local planning authority approves the land use and layout of the development under Act 172.
- Building plan approval The PSP submits the building plans to the local authority. No building may be erected without its prior written permission (section 70(1), Act 133).
- Notice of commencement Notice of the intention to start building is given in Form B (by-law 22, UBBL).
- Construction and stage certification Each component is certified in Forms G1 to G21 by the contractor and the relevant qualified person.
- CCC issued by the PSP Once every condition in by-law 25 is met, the PSP issues Form F.
- Copies to the local authority and board Within 14 days, the PSP lodges copies of the CCC and Forms G1 to G21 with the local authority and the Board of Architects Malaysia or Board of Engineers Malaysia.
- Vacant possession (VP) The developer hands over the home and keys after the CCC is issued and water and electricity are ready for connection.
Step 1: planning permission
Section 19(1) of Act 172 says a person shall not commence, undertake or carry out any development without planning permission. Under section 22, the local planning authority may grant planning permission absolutely or subject to conditions, or refuse it.
Planning permission also has a time limit. Section 24 says planning permission lapses 12 months after it is granted if the development has not commenced, unless extended. An extension must be applied for before it lapses.
For a buyer, planning permission means the use of the land for housing and the estate layout have been approved. It does not yet mean the design of your home has been approved.
Step 2: building plan approval
Section 70(1) of Act 133 says, in short, that no person shall erect any building without the prior written permission of the local authority. Section 70(2) requires anyone who intends to erect a building to submit plans and specifications through a PSP or SP to the local authority and the relevant statutory authorities.
All plans, specifications and calculations must be prepared and certified by the PSP or SP, and signed by the owner (or its agent) and the PSP or SP (section 70(19)). The number and date of these approved plans are what the CCC refers back to later.
Step 3: construction and stage certification (Forms G1 to G21)
The CCC system was introduced by an amendment to Act 133 in 2007 and came into force on 12 April 2007, replacing the Certificate of Fitness for Occupation (CF). A key part of the system is stage certification: 21 building components are certified one by one in Forms G1 to G21, set out in the Second Schedule of the UBBL.
Each form is signed by the party that did the work (the contractor or trade contractor) and the qualified person who supervised it. They certify that the work complies with the approved plans, and accept full responsibility for it. Where a component is not part of the project (for example a lift in a terraced house), the PSP certifies on that form that it is not applicable.
| Form | Component | Signed by |
|---|---|---|
| G1 | Earthworks | Contractor and SP |
| G2 | Setting out | Contractor, licensed land surveyor and PSP |
| G3 | Foundations | Contractor and SP |
| G4 | Structural | Contractor and SP |
| G5 | Internal water plumbing | Trade contractor and SP |
| G6 | Internal sanitary plumbing | Trade contractor and SP |
| G7 | Internal electrical | Trade contractor and SP |
| G8 | Fire-fighting (passive) | Trade contractor and PSP |
| G9 | Fire-fighting (active) | Trade contractor and SP |
| G10 | Mechanical ventilation | Trade contractor and SP |
| G11 | Lift or escalator installation | Trade contractor and SP |
| G12 | Building | Trade contractor and PSP |
| G13 | External water supply system | Trade contractor and SP |
| G14 | Sewerage reticulation | Trade contractor and SP |
| G15 | Sewerage treatment plant | Trade contractor and SP |
| G16 | External electrical supply system | Trade contractor and SP |
| G17 | Road and drain | Trade contractor and SP |
| G18 | Street lighting | Trade contractor and SP |
| G19 | External main drain | Trade contractor and SP |
| G20 | Telecommunications | Trade contractor and SP |
| G21 | Landscape | Trade contractor and architect or landscape architect |
According to a summary by IPM (2022), some forms must be accompanied by a confirmation letter from another agency, for example G8 and G9 from the Fire and Rescue Department (Bomba), G11 from the Department of Occupational Safety and Health (DOSH), G13 from the water authority, G14 and G15 from the sewerage agency (IWK), and G16 from TNB. IPM also says the PSP notifies the local authority once Forms G1 to G3 (the substructure stage) are certified.
Step 4: the PSP issues the CCC
Section 70(20) of Act 133 says no CCC shall be issued except by a PSP, in accordance with the prescribed time, manner and procedure. By-law 25(1) of the UBBL says the PSP issues the CCC in Form F only when all four of these conditions are met:
| Condition | What it means |
|---|---|
| (a) Local authority technical conditions | All technical conditions imposed by the local authority have been complied with. |
| (b) Forms G1 to G21 | All stage certifications have been duly certified and received by the PSP. |
| (c) Essential services | Access roads, landscape, car parks, drains, sanitary, water and electricity installations, communication, fire hydrants, sewerage, refuse disposal and fire lifts (where required) have been provided. |
| (d) PSP's declaration | The PSP certifies in Form F that they supervised the construction and that, to the best of their knowledge, the building was built in accordance with the Act, the by-laws and the approved plans. |
By issuing the CCC, the PSP accepts full responsibility for it and certifies that the building is safe and fit for occupation (by-law 25(2)). Section 70(21) of Act 133 also places duties on the PSP to supervise the construction, ensure it conforms with the approved plans and the local authority’s technical conditions, and ensure the building is safe and fit for occupation.
The local authority’s role
The local authority does not issue the CCC, but it still has powers. Under by-laws 25(4) to 25(13):
- The local authority may inspect building works at any stage and give the PSP written notice to rectify a non-compliance.
- The local authority may direct the PSP in writing to withhold the CCC.
- The PSP must rectify the non-compliance within 21 days of the notice, or a longer period approved by the local authority.
- Once the PSP confirms the rectification is done, the local authority must inspect within 14 days. If it does not inspect in that time, it is deemed satisfied.
- The CCC may not be issued until every non-compliance has been rectified.
Copies lodged within 14 days
By-law 25(3) requires the PSP, within 14 days of issuing a CCC or partial CCC, to lodge a copy of it together with Forms G1 to G21 with the local authority and with the Board of Architects Malaysia or Board of Engineers Malaysia. Failing to do so is an offence (by-law 28). The Board of Architects Malaysia says the documents are submitted to the local authority and through the myLAM Portal to LAM or BEM.
Partial CCC (Form F1)
By-law 27 allows the PSP to issue a partial CCC for a completed part of a building, subject to the local authority’s conditions, and only if the essential services for that part have been provided. But note: the definition of CCC in the Schedule G SPA does not include a partial CCC. So for a landed home under Schedule G, VP requires a full CCC.
Step 5: VP
Clause 25 of the Schedule G SPA requires the developer, at its own cost, to comply with all the authority’s requirements for the issue of the CCC. Clause 26(1) then says the developer lets the buyer into possession upon:
- the issue of the CCC;
- water and electricity supply being ready for connection to the home;
- the buyer having paid all amounts due under the SPA; and
- completion of any agreed alteration or additional work (if any).
Clause 26(2) adds that delivery of VP must be supported by the CCC and includes handing over the keys.
Why the CCC matters to you
| What | Link to the CCC | Source |
|---|---|---|
| Occupying the home | Occupying, or permitting the occupation of, a building without a CCC is an offence; the maximum penalty is a fine not exceeding RM250,000 or imprisonment not exceeding 10 years or both | Section 70(27)(f), Act 133 |
| Handover of keys | VP only after the CCC is issued, and it must be supported by the CCC | Clause 26, Schedule G |
| Water and electricity | Water, electricity, sewerage and other essential services must be provided before the CCC; VP also requires water and electricity ready for connection | By-law 25(1)(c), UBBL; clause 26(1)(b), Schedule G |
| Final payments and the loan | 17.5% of the price is paid on the date of VP, together with the 2.5% linked to the title and the 5% retention; all depend on VP, and VP depends on the CCC | Third Schedule, items 3 to 5 |
| Tribunal claims | LAD and other claims must be filed no later than 12 months from the date the CCC is issued | Tribunal FAQ, KPKT |
The CCC date also matters for late-delivery claims. If your home is handed over late, note the CCC date, because the 12-month period to claim LAD at the Tribunal runs from that date.
How to check your home’s CCC
Two hypothetical examples: checking Form F before collecting the keys, and working out dates from the CCC date
Example: checking the CCC before collecting the keys
Hypothetical names and details. Puan Siti receives a VP notice. She asks her lawyer for a copy of Form F. She finds her lot number within the list of lots, the approved plan's number and date are stated, and the PSP is a professional architect with a Board of Architects Malaysia registration number. The form is Form F (a full CCC), not Form F1. She keeps a copy with her SPA and notes the CCC date for any late-delivery claim.
Example: working out dates from the CCC
Hypothetical dates. The CCC is issued on 3 June. The PSP must lodge copies of the CCC and Forms G1 to G21 with the local authority and the board within 14 days, by 17 June at the latest. If the home is handed over more than 24 months after the SPA and the buyer wants to claim LAD at the Tribunal, the claim must be filed no later than 12 months from 3 June.
CCC compared with CPC
Buyers sometimes confuse the CCC with the CPC (Certificate of Practical Completion). The CCC is a statutory requirement issued by the PSP stating the building is safe to occupy. The CPC is issued by the architect or superintending officer under the building contract, and only confirms that the physical works in the contract are complete. The CPC is a contractual matter between the project owner and the contractor. It does not replace the CCC.
Common mistakes
- Collecting the keys without seeing the CCC. Ask for a copy of Form F every time.
- Accepting a partial CCC as enough. Under a Schedule G SPA, VP requires a full CCC.
- Assuming the local authority issues the CCC. Since 2007, the PSP issues it; the local authority regulates and can direct that it be withheld.
- Confusing the CPC with the CCC. A CPC does not allow occupation.
- Not noting the CCC date. This date starts the 12-month period for LAD claims at the Tribunal.
- Moving in and renovating before formal VP. Occupying a building without a CCC is an offence.
Quick checklist
Next step
To understand how payments link to each stage up to VP, read construction stages and the payment schedule. For handover day, read the handover inspection guide and the Quality & Handover page. To see how RumahHQ reports project progress openly, see Transparency. If you are looking for a home, Register Interest. It is free and non-binding.
Questions
Who issues the CCC?
The CCC (Form F) is issued by the Principal Submitting Person (PSP), the professional architect, professional engineer or registered building draughtsman who submitted the building plans, under by-law 25 of the UBBL 1984 and section 70(20) of Act 133.
What are Forms G1 to G21?
They are 21 stage certification forms for the building's components, from earthworks (G1) to landscape (G21). All of them must be certified and received by the PSP before the CCC is issued.
Can a developer hand over the keys without a CCC?
Under clause 26(1) of the Schedule G SPA, the developer delivers vacant possession upon the issuance of the CCC. The Schedule G definition of CCC does not include a partial CCC. Occupying a building without a CCC is an offence under section 70(27)(f) of Act 133.
How long does the PSP have to lodge copies of the CCC with the local authority?
By-law 25(3) of the UBBL requires the PSP to lodge a copy of the CCC and Forms G1 to G21 with the local authority and the Board of Architects Malaysia or Board of Engineers Malaysia within 14 days of issuing the CCC.
What is the difference between a CCC and a CPC?
The CCC is a statutory requirement stating the building is safe to occupy. The CPC (Certificate of Practical Completion) is a contract document between the project owner and the contractor confirming the physical works in the contract are complete.
Sources
(9)
- KPKT (JKT), Uniform Building By-Laws 1984, incorporating amendments K.P.U. 6/2007 — read 2026-09-24
- Street, Drainage and Building Act 1974 [Act 133], updated text as at 1 June 2014 (copy published by PPj) — read 2026-09-24
- Low & Partners, Town and Country Planning Act 1976, Part 2 — read 2026-09-24
- Board of Architects Malaysia (LAM), Certificate of Completion & Compliance (CCC) — read 2026-09-24
- IPM, Form G for Certificate of Completion and Compliance (CCC) (31 December 2022) — read 2026-09-24
- IPM, CCC vs CPC — read 2026-09-24
- Housing Development (Control and Licensing) Regulations 1989, Schedule G (as amended 2015), copy published by REHDA Melaka — read 2026-09-24
- KPKT, Soalan Lazim Tribunal Tuntutan Pembeli Rumah (Homebuyer Claims Tribunal FAQ) — read 2026-09-24
- Bernama, prospective buyers urged to check projects and developers on TEDUH (7 September 2026) — read 2026-09-24
Related guides
-
Construction Process Construction Stages and the Progressive Payment Schedule Each stage of building a landed home mapped to Schedule G progressive payments, the architect's certificate, LPPSA releases and interest during construction. 14 min read
-
Buying a First Home New Home Costs in Malaysia: Stamp Duty & Legal Fees Every cost of buying a new home: legal fees, stamp duty, disbursements, insurance, utility deposits and taxes, with worked examples and when each is paid. 12 min read
-
Buying a First Home Registration of Interest, Booking Fee or SPA? Registration of interest, booking fees and the SPA compared: what regulation 11(2) says, the PJD Regency case, KPKT's 2026 position and your rights. 11 min read