Construction Stages and the Progressive Payment Schedule
Pasukan RumahHQ · Published 24 September 2026 · Updated 24 September 2026 · 14 min read
In brief
- The Third Schedule of the Schedule G SPA sets the same stage percentages in every SPA, starting with 10% immediately upon signing.
- Every payment notice must come with a certificate signed by the developer's architect or engineer; you pay within 30 days of receiving it.
- With a bank loan you usually pay interest only on the amount released during construction, so budget for interest that rises month by month.
When you buy a landed home that has not been built yet, you do not pay the price in one go. The price is paid bit by bit, following the progress of work on site. Each time a stage is completed, the developer sends a payment notice, and you (or your bank or LPPSA on your behalf) pay the percentage set for that stage.
This guide explains each stage of building a landed home, the percentage the law sets for each stage, how the architect’s certificate triggers each billing, how banks and LPPSA release money, and how much interest you might pay while the house is still being built. General information only, not legal/financial/tax advice.
Key terms
- SPA: the sale and purchase agreement between you and the developer.
- Schedule G: the statutory SPA form for a landed home (land and building) under the Housing Development (Control and Licensing) Regulations 1989. The developer cannot change its main terms.
- Third Schedule: the part of the Schedule G SPA that lists the schedule of payment of the purchase price.
- Progressive payment: payment according to the stage of work completed.
- Architect’s certificate: a certificate signed by the developer’s architect or engineer confirming that a piece of work is complete.
- VP: vacant possession, the handover of the home and keys to you.
- CCC: Certificate of Completion and Compliance, which states that the home is complete, safe and fit for occupation.
- Progressive interest: interest on a bank loan charged on the amount already released to the developer before the home is complete.
Overview: from SPA to keys
Payment for a home under construction follows the same cycle each time. The diagram shows the cycle for each stage.
- Work completed on siteFor example the foundation
- Architect's certificateThe developer's architect or engineer inspects and signs a certificate
- Payment noticeA written notice to you, together with that certificate
- Payment within 30 daysYou, your bank or LPPSA pay that stage's percentage
- Next stageThe cycle repeats until VP, the title and the end of the retention period
- Work completed on site The developer's contractor completes a stage, for example the foundation.
- Architect's certificate The developer's architect or engineer inspects and signs a certificate that the work is complete.
- Payment notice The developer sends you a written notice, together with that certificate.
- Payment within 30 days You, your bank or LPPSA pay that stage's percentage within 30 days.
- Next stage The cycle repeats until VP, the title and the end of the retention period.
The law sets several important points in this process:
- Every claim must be certified. Clause 5(2) of Schedule G requires every payment notice to be supported by a certificate signed by the developer’s architect or engineer in charge of the development. That certificate is proof that the work has been completed.
- You pay for completed work, not in order. Clause 5(1) says the developer is not bound to build in the order of the Third Schedule. If later work damages completed work, the developer must repair it at its own cost before VP.
- The payment period is 30 days. The Third Schedule requires payment within 30 days after you receive the developer’s written notice.
- Late payment charges. If an instalment is unpaid after 30 days, clause 10(1) allows late payment charges at 10% a year, calculated from day to day. Clause 10(2) says the charge cannot be imposed if the delay is caused by a payment notice that is incomplete or not supported by the certificate.
- Apply for your loan early. If you want a loan, clause 6(1) requires you to make a written application within 30 days after receiving the stamped copy of the SPA.
Construction stages and payment percentages
The table maps each stage of building a landed home to its item in the Third Schedule of the Schedule G SPA. These percentages are set in the statutory form, so they are the same in every Schedule G SPA.
| Construction stage | Third Schedule item | Percentage | Cumulative |
|---|---|---|---|
| SPA signing (site preparation may be under way, but it has no payment item of its own) | 1. Immediately upon signing the SPA | 10% | 10% |
| Foundation | 2(a) The foundation of the building | 10% | 20% |
| Structure | 2(b) The structural framework of the building | 15% | 35% |
| Walls | 2(c) The walls of the building with door and window frames placed in position | 10% | 45% |
| Roof and M&E (mechanical and electrical) | 2(d) The roofing, electrical wiring, plumbing (without fittings), gas piping (if any) and internal telecommunication trunking and cabling | 10% | 55% |
| Finishes | 2(e) The internal and external finishes including the wall finishes | 10% | 65% |
| External works: sewerage | 2(f) The sewerage works serving the building | 5% | 70% |
| External works: drains | 2(g) The drains serving the building | 2.5% | 72.5% |
| External works: roads | 2(h) The roads serving the building | 2.5% | 75% |
| Handover | 3. On the date of VP, with water and electricity supply ready for connection | 17.5% | 92.5% |
| Title | 4. On the date of VP, where the original title registered in your name has been delivered | 2.5% | 95% |
| Defect-period retention | 5. On the date of VP, held by the developer's solicitor as stakeholder: 2.5% released 8 months after VP and 2.5% released 24 months after VP | 5% | 100% |
What happens at each stage
Site preparation. The site is cleared, levelled and the position of the houses marked out. The Third Schedule has no payment item for this work. The first 10% is paid when the SPA is signed, regardless of progress.
Foundation. The foundation carries the weight of the house into the ground. For most landed homes this involves piles or pad footings, ground beams and the ground floor slab. Once the foundation is complete and certified, the developer may claim 10%.
Structure. Columns, beams and upper floor slabs are built. This is the largest percentage in the construction phase, 15%.
Walls. Brick or block walls go up, and door and window frames are fixed in position. Payment of 10%.
Roof and M&E. The roof goes on, and the hidden work is put in: electrical wiring, water piping (without fittings such as taps and sinks), gas piping if any, and internal telecommunication cabling. Payment of 10%.
Finishes. Plaster, paint, tiles, ceilings and external finishes. Payment of 10%.
External works. The sewerage (5%), drains (2.5%) and roads (2.5%) serving your home. This work is usually done for the whole estate, not house by house.
VP, title and retention. The remaining 25% is paid on the date of VP: 17.5% when the home is handed over with water and electricity ready for connection, 2.5% linked to the title, and 5% held by the developer’s solicitor as security for the defect liability period. For VP, the developer must also obtain the CCC first (clause 26). Read what is a CCC for the full explanation.
How long does each stage take?
No official source sets a duration for each stage. Actual durations depend on the size of the project, the soil, the construction method, the weather and approvals. What the law does set is the overall period: clause 24(1) of Schedule G requires VP to be delivered within 24 months of the SPA date. If it is late, clause 24(2) requires the developer to pay liquidated damages (LAD) at 10% a year of the purchase price, calculated from day to day.
The payment timeline in one diagram
This diagram shows the main events in order and the cumulative percentage paid.
- SPA signed: 10% The first payment. The 24-month period for VP starts running.
- Foundation and structure: 35% Two certified claims, 10% and 15%.
- Walls, roof and M&E: 55% Two claims of 10% each.
- Finishes and external works: 75% Finishes 10%, sewerage 5%, drains 2.5% and roads 2.5%.
- CCC issued A precondition for VP under clause 26.
- VP and keys: 95% 17.5% on VP, and 2.5% linked to the title. The 24-month defect liability period starts.
- 8 months after VP The developer's solicitor releases 2.5% of the retention, unless a defect notice is still unresolved.
- 24 months after VP: 100% The final 2.5% retention is released, on the same condition.
How the bank and LPPSA release payments
If you finance the home with a loan, you usually pay the first 10% from your own money (or according to your financing margin), and the balance is paid by the bank or LPPSA directly to the developer, stage by stage.
Bank loan
Banks release money progressively. For example, RHB states that for properties under construction, the bank releases the progressive payment to the developer based on the claim made upon completion of each construction stage, as certified by the Architect’s Certificate.
The usual flow is: the developer sends the payment notice and architect’s certificate to you and the bank; you (or your lawyer) check the documents are complete; the bank releases that stage’s amount to the developer. Check with your bank whether it needs your signature or confirmation for each release.
LPPSA
For Type 3 financing (buying a home under construction from a developer), LPPSA’s Housing Financing Guideline Bil.1/2026 says the financing is released up to 100% to the developer, and LPPSA accepts progressive payment claims and Architect’s Certificates from the developer. For the full application steps, read how to apply for LPPSA for a developer home.
| Point | Bank loan | LPPSA Type 3, landed home |
|---|---|---|
| How money is released | Progressively to the developer, based on claims and the architect's certificate | Up to 100% to the developer, based on progressive payment claims and the architect's certificate |
| Interest or profit during construction | Usually charged on the amount already released (progressive interest) | Calculation starts the month after progress payments of 95% or more are released, or in the 25th month from approval, whichever is earlier |
| Full instalments start | Usually after the loan is fully released; check your letter of offer | Monthly deductions start in the 25th month from approval, or after the 95% progress payment is released, whichever is earlier |
Interest during construction (bank loans)
With a bank loan, you usually do not pay the full instalment while the house is being built. Instead, you pay interest only on the part of the loan already released to the developer. The more stages are completed, the more has been released, and the higher the monthly interest. The full instalment (principal and interest) starts once the loan is fully released, under the terms of your letter of offer.
A simple way to estimate it is:
Monthly interest ≈ amount released × annual interest rate ÷ 12
Banks may calculate by the number of days in the month, so your bank’s figure will differ slightly.
Hypothetical example: monthly interest on a RM400,000 home, RM360,000 loan and an assumed rate of 4% a year
Example: interest during construction on a bank loan
Hypothetical figures, for illustration only, not a RumahHQ price. The home costs RM400,000. You pay 10% (RM40,000) at the SPA from your own money, and the bank finances 90% (RM360,000). The assumed interest rate is 4% a year. This rate is an example assumption, not a market rate.
After the foundation is complete, the bank releases 10% of the price (RM40,000). Monthly interest ≈ RM40,000 × 4% ÷ 12 = RM133.33. After the structure, the total released becomes RM100,000, so interest is about RM333.33 a month. The table shows each stage.
| After stage | Released for this stage | Total released | Estimated interest a month |
|---|---|---|---|
| Foundation (10%) | RM40,000 | RM40,000 | RM133.33 |
| Structure (15%) | RM60,000 | RM100,000 | RM333.33 |
| Walls (10%) | RM40,000 | RM140,000 | RM466.67 |
| Roof and M&E (10%) | RM40,000 | RM180,000 | RM600.00 |
| Finishes (10%) | RM40,000 | RM220,000 | RM733.33 |
| Sewerage (5%) | RM20,000 | RM240,000 | RM800.00 |
| Drains (2.5%) | RM10,000 | RM250,000 | RM833.33 |
| Roads (2.5%) | RM10,000 | RM260,000 | RM866.67 |
| VP (17.5%) | RM70,000 | RM330,000 | RM1,100.00 |
| Title (2.5%) and retention (5%) | RM30,000 | RM360,000 | Loan fully released; full instalment per letter of offer |
The total interest you pay during construction depends on how long the released amount stays at each level. If the project moves quickly to the later stages, more months are paid at the higher interest; if the early stages take longer, the monthly interest stays low for longer. Budget for interest that rises month by month, not a fixed amount.
Hypothetical example: checking a payment notice for item 2(b), the structural framework
Example: checking a payment notice
Hypothetical figures. Encik Hafiz buys a home at RM400,000. He receives a payment notice for item 2(b), the structural framework. He checks three things: (1) the notice comes with a certificate signed by the developer's architect or engineer; (2) the amount claimed is 15% × RM400,000 = RM60,000; (3) the date he received the notice, because the 30-day period starts from that date. Everything is correct, so he forwards a copy to his bank straight away so the release is not late.
What to check at each stage
| Stage | What to check |
|---|---|
| Before the SPA | The developer's licence and advertising and sales permit (APDL) are stated in the SPA; the SPA uses the Schedule G form; the price and unit details are correct. |
| After the SPA | The 10% payment is recorded with a receipt; the loan application is made within 30 days of receiving the stamped SPA. |
| Every payment notice | An architect's or engineer's certificate is attached; the Third Schedule item is stated; amount = percentage × price; the date received is recorded. |
| Foundation and structure | Look at progress photos or visit the site if it is safe and allowed; make sure the stage claimed actually looks complete. |
| Walls, roof and M&E | Door and window frames are in place before item 2(c) is claimed; roof and wiring before item 2(d). |
| Finishes and external works | Sewerage, drains and roads are claimed separately; check each item is claimed only once. |
| Before VP | The CCC has been issued; water and electricity are ready for connection; check the final amount claimed. |
| After VP | Inspect for defects straight away; remember the 5% retention and the 8-month and 24-month dates. |
At RumahHQ, each project’s progress is published on public progress pages, so buyers can see for themselves which stage has been reached. Read more on the Transparency and How We Build pages.
Common mistakes
- Not recording the date a notice was received. The 30-day period runs from the date you receive the notice, so keep the envelope, email or delivery receipt.
- Forwarding the notice to the bank late. A late release can lead to late payment charges of 10% a year under clause 10(1), unless the notice itself was incomplete.
- Not checking the architect’s certificate. A notice without a certificate does not meet clause 5(2).
- Assuming full instalments start at the SPA. With a bank loan you usually pay interest only on the amount released during construction. For LPPSA Type 3 on a landed home, the 25th-month or 95% rule applies.
- Not budgeting for rising interest. Monthly interest goes up each time a stage is paid.
- Forgetting the 5% retention. It is held by the developer’s solicitor and helps protect you during the defect liability period.
Quick checklist
Next step
Once the home is complete, the next important step is the inspection at handover. Read the handover inspection guide and the Quality & Handover page. If you have not checked your financing eligibility yet, read check eligibility before buying your first home, then Register Interest for upcoming RumahHQ projects. Registration of interest is free and non-binding.
Questions
What percentage is paid when signing the SPA for a landed home?
Under item 1 of the Third Schedule of the Schedule G SPA, 10% of the purchase price is payable immediately upon signing the agreement.
Who confirms that a construction stage is complete?
Clause 5(2) of Schedule G requires every notice requesting payment to be supported by a certificate signed by the developer's architect or engineer in charge of the housing development.
How long do I have to pay after receiving a payment notice?
The Third Schedule sets 30 days after you receive the developer's written notice. If payment is late, clause 10(1) allows late payment charges of 10% a year, calculated from day to day.
Do I pay interest while the house is being built?
With a bank loan, interest is usually charged only on the amount already released to the developer. For LPPSA Type 3 financing of a landed home, Guideline Bil.1/2026 says profit calculation starts after the 95% progress payment is released or in the 25th month from approval, whichever is earlier.
Must the developer build in the order of the schedule?
No. Clause 5(1) says the developer is not bound to commence or complete the works in the order of the Third Schedule. You pay according to the stages completed.
Sources
(4)
- Housing Development (Control and Licensing) Regulations 1989, Schedule G (as amended 2015), copy published by REHDA Melaka — read 2026-09-24
- LPPSA, Garis Panduan Pembiayaan Perumahan LPPSA Bil.1/2026 (Housing Financing Guideline) — read 2026-09-24
- RHB, Commodity Murabahah Term Financing-i for Home — read 2026-09-24
- MYRA, What Is Progressive Interest and Billing? — read 2026-09-24
Related guides
-
Construction Process Handover Inspection & Defect Liability Period Guide How to inspect a new home at handover: tools, a room-by-room checklist, recording defects, notices within the 24-month DLP and the Homebuyer Tribunal route. 13 min read
-
Buying a First Home New Home Costs in Malaysia: Stamp Duty & Legal Fees Every cost of buying a new home: legal fees, stamp duty, disbursements, insurance, utility deposits and taxes, with worked examples and when each is paid. 12 min read
-
Buying a First Home Registration of Interest, Booking Fee or SPA? Registration of interest, booking fees and the SPA compared: what regulation 11(2) says, the PJD Regency case, KPKT's 2026 position and your rights. 11 min read